Large-scale estimation of electricity distribution grid reinforcement requirements for the energy transition – A 2030 Spanish case study

Thumbnail
Ver/
IIT-24-331R (9.752Mb)
IIT-24-331R_preview (3.478Kb)
Fecha
2024-12-01
Autor
Herding, Leslie
Pérez Bravo, Manuel
Barrella, Roberto
Cossent Arín, Rafael
Rivier Abbad, Michel Luis
Estado
info:eu-repo/semantics/publishedVersion
Metadatos
Mostrar el registro completo del ítem
Mostrar METS del ítem
Ver registro en CKH

Refworks Export

Resumen
 
 
The increasing interest in distributed energy resources (DER) challenges electricity distribution grids to host the required distributed generation (DG) capacities and the expected load increase from electrification. However, a large-scale estimation of costs for integrating DER into low, medium, and high voltage distribution networks has yet to be addressed. This paper contributes a model for the large-scale estimation of the impact of distributed generation, electric vehicles and heat pumps on network reinforcement requirements. The model allocates future DER geographically to 8000 Spanish peninsular municipalities. The large-scale model considers low, medium and high voltage distribution grids. The resulting distribution grid investment is determined via individualised reinforcement costs for each of the 47 peninsular Spanish provinces, distinguishing between urban, semi-urban, rural concentrated and rural dispersed configurations of distribution networks. A 2030 case study shows that the geographical allocation of DG is not aligned with the allocation of load electrification, leading to total investment requirements of 2627 MEUR. This finding points out that distribution system operators covering different parts of the territory are likely to face a variety of challenges that are not aligned across the territories, requiring regulation to account for a variation of distribution grid expansion requirements for the energy transition.
 
URI
https:doi.org10.1016j.egyr.2024.11.026
http://hdl.handle.net/11531/100621
Large-scale estimation of electricity distribution grid reinforcement requirements for the energy transition – A 2030 Spanish case study
Tipo de Actividad
Artículos en revistas
ISSN
2352-4847
Materias/ categorías / ODS
Instituto de Investigación Tecnológica (IIT)
Palabras Clave

Distribution grids; Distributed generation; Electric vehicles; Heat pumps
Colecciones
  • Artículos

Repositorio de la Universidad Pontificia Comillas copyright © 2015  Desarrollado con DSpace Software
Contacto | Sugerencias
 

 

Búsqueda semántica (CKH Explorer)


Listar

Todo DSpaceComunidades & ColeccionesPor fecha de publicaciónAutoresTítulosMateriasPor DirectorPor tipoEsta colecciónPor fecha de publicaciónAutoresTítulosMateriasPor DirectorPor tipo

Mi cuenta

AccederRegistro

Repositorio de la Universidad Pontificia Comillas copyright © 2015  Desarrollado con DSpace Software
Contacto | Sugerencias