dc.contributor.advisorSánchez Mingarro, Matías Juanes-ES
dc.contributor.authorVicente Donaire, Pabloes-ES
dc.contributor.otherUniversidad Pontificia Comillas, Escuela Técnica Superior de Ingeniería (ICAI)es_ES
dc.date.accessioned2023-12-19T15:46:24Z
dc.date.available2023-12-19T15:46:24Z
dc.date.issued2024es_ES
dc.identifier.urihttp://hdl.handle.net/11531/85996es_ES
dc.descriptionGrado en Ingeniería en Tecnologías Industrialeses_ES
dc.description.abstractEste proyecto de fin de grado se centra en modernizar la subestación de Sant Antoni en Ibiza utilizando sistemas de almacenamiento de energía en baterías (BESS). El objetivo es mejorar la eficiencia, confiabilidad e integración de energías renovables en la red eléctrica de la isla, atendiendo las crecientes demandas energéticas y promoviendo la transición hacia fuentes de energía más sostenibles. La motivación principal es fortalecer la conexión eléctrica entre Ibiza y la península, gestionando también las fluctuaciones en la demanda eléctrica causadas por el turismo y el clima. El BESS permitirá almacenar energía durante periodos de baja demanda y liberarla en momentos de alta demanda, mejorando así la estabilidad y confiabilidad del suministro eléctrico. Además, reforzará la conexión con la península. Este proyecto se alinea con el Plan Nacional Integrado de Energía y Clima (PNIEC), que establece que el 74% de la energía debe provenir de fuentes renovables para 2030. La iniciativa también busca aumentar la capacidad de almacenamiento en la subestación mediante la tecnología BESS, optimizando los recursos energéticos y mejorando la eficiencia del sistema. Se asegura el cumplimiento de normativas medioambientales y de seguridad para garantizar que la planta no tenga impactos adversos significativos y mantenga altos estándares de seguridad laboral. La instalación contará con 18 contenedores de baterías, 36 inversores y un sistema de almacenamiento con una capacidad de 45,14 MW y 90,28 MWh. Las obras civiles incluyen movimientos de tierra, cimentación, canalización de cableado, saneamientos y construcción de accesos y vallado perimetral. El presupuesto total del proyecto es de 86.670.500 euros, incluyendo costos de ingeniería, materiales y construcción. Un estudio de impacto ambiental asegura que el BESS no tenga efectos negativos significativos en el entorno. En resumen, la planta BESS en Sant Antoni de Portmany representa un avance significativo en la gestión y almacenamiento de energía, contribuyendo a la sostenibilidad y resiliencia del sistema eléctrico de Ibiza y apoyando la lucha global contra el cambio climático.es-ES
dc.description.abstractThis final degree project focuses on modernizing the Sant Antoni substation in Ibiza using battery energy storage systems (BESS). The objective is to improve efficiency, reliability, and the integration of renewable energies into the island's electrical grid, addressing the increasing energy demands and promoting the transition to more sustainable energy sources. The primary motivation is to strengthen the electrical connection between Ibiza and the mainland, also managing the fluctuations in electrical demand caused by tourism and climate. The BESS will allow energy to be stored during periods of low demand and released during peak times, thus improving the stability and reliability of the power supply. Additionally, it will reinforce the connection with the mainland. This project aligns with the National Integrated Energy and Climate Plan (PNIEC), which stipulates that 74% of energy should come from renewable sources by 2030. The initiative also aims to increase the storage capacity at the substation through BESS technology, optimizing energy resources and improving system efficiency. Compliance with environmental and safety regulations is ensured to guarantee that the plant does not have significant adverse impacts and maintains high standards of workplace safety. The installation will feature 18 battery containers, 36 inverters, and a storage system with a capacity of 45.14 MW and 90.28 MWh. The civil works include earthmoving, foundation work, cable channelling, sanitation, and the construction of access routes and perimeter fencing. The total project budget is €86,670,500, which includes costs for engineering, materials, and construction. An environmental impact study ensures that the BESS will not have significant negative effects on the surroundings. In summary, the BESS plant in Sant Antoni de Portmany represents a significant advancement in energy management and storage, contributing to the sustainability and resilience of Ibiza's electrical system while supporting global efforts to combat climate change.en-GB
dc.format.mimetypeapplication/pdfes_ES
dc.language.isoes-ESes_ES
dc.rightsAttribution-NonCommercial-NoDerivs 3.0 United Stateses_ES
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/3.0/us/es_ES
dc.subject.otherKTI-electricidad (GITI-E)es_ES
dc.titleTransformación energética en las islas: implementación de tecnología BESS en la subestación Sant Antoni, Ibiza (66kV)es_ES
dc.typeinfo:eu-repo/semantics/bachelorThesises_ES
dc.rights.accessRightsinfo:eu-repo/semantics/openAccesses_ES
dc.keywordsSubestación de Sant Antoni, Ibiza, sistemas de almacenamiento de energía en baterías (BESS), interconexión eléctrica, demanda eléctrica, sostenibilidad, resiliencia, Plan Nacional Integrado de Energía y Clima (PNIEC), tecnología BESS.es-ES
dc.keywordsSant Antoni Substation, Ibiza, battery energy storage systems (BESS), electrical interconnection, electrical demand, sustainability, resilience, National Integrated Energy and Climate Plan (PNIEC), BESS technology.en-GB


Ficheros en el ítem

Thumbnail
Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

Attribution-NonCommercial-NoDerivs 3.0 United States
Excepto si se señala otra cosa, la licencia del ítem se describe como Attribution-NonCommercial-NoDerivs 3.0 United States