Título : Proactive transmission expansion planning with storage considerations
Autor : González Romero, Isaac Camilo
Wogrin, Sonja
Gómez San Román, Tomás
Fecha de publicación : 1-abr-2019
Resumen : Under the current European market environment, transmission companies have to decide network expansion by maximizing social welfare. However, generation companies (GENCOs) decide their capacity expansion with the aim of maximizing their own profit. This process, in addition to the increasing penetration of renewable energy, storage and distributed generation, might represent a rupture between short and long-term signals. Therefore, this paper proposes a bi-level formulation for the generation and transmission coordination problem (GEPTEP). We consider a proactive framework in which a centralized TSO represents the upper level while the decentralized GENCOs, that trade in the market, represent the lower level. As a novel feature, an enhanced representative period framework is employed, which allows us to consider operation in both short and long-term storage technologies. A case study is presented to compare the results between perfect and imperfect competition in the market.
Under the current European market environment, transmission companies have to decide network expansion by maximizing social welfare. However, generation companies (GENCOs) decide their capacity expansion with the aim of maximizing their own profit. This process, in addition to the increasing penetration of renewable energy, storage and distributed generation, might represent a rupture between short and long-term signals. Therefore, this paper proposes a bi-level formulation for the generation and transmission coordination problem (GEPTEP). We consider a proactive framework in which a centralized TSO represents the upper level while the decentralized GENCOs, that trade in the market, represent the lower level. As a novel feature, an enhanced representative period framework is employed, which allows us to consider operation in both short and long-term storage technologies. A case study is presented to compare the results between perfect and imperfect competition in the market.
Descripción : Artículos en revistas
URI : https://doi.org/10.1016/j.esr.2019.02.006
ISSN : 2211-467X
Aparece en las colecciones: Artículos

Ficheros en este ítem:
Fichero Descripción Tamaño Formato  
IIT-19-021A.pdf2,91 MBAdobe PDFVista previa
Visualizar/Abrir
IIT-19-021A2,91 MBUnknownVisualizar/Abrir
IIT-19-021A2,91 MBUnknownVisualizar/Abrir


Los ítems de DSpace están protegidos por copyright, con todos los derechos reservados, a menos que se indique lo contrario.